S2 expressway
More [+]
Marynarska in progress
S8 under construction
Marynarska south side
S2 dual carriageway under construction.
S2 in progress
Investor: GDDKiA
General Contractor: WARBUD S.A.
P.B.I. PEBIS sp. z o.o. has started to construct storm water network on the S2 expressway
Within Our contract we will built storm water network :
1. from pipes PP DN200-DN1100 - designed length 15265m
2. from pipes PEHD DN160-DN400 - designed length 2941m
3. rainforcement chamber DN1200-DN3200 - 454 items
4. concrete chamber DN500 - 712 items
5. separator of petroleum substances - 20 items (form Q=4,16l/s to Q=730l/s)
6. settler suspensions - 20 items (form Q=4,16l/s to Q=730l/s)
7. rainwater pumping station - 6 items (from Q=40l/s to Q=150l/s)
S8 dual carriageway under construction.
The works are still going on.
The works are still going on.
Investor: GDDKiA
General Contractor: Przedsiębiorstwo Usług Technicznych "Intercor" Sp. z o.o.
P.B.I. PEBIS sp. z o.o. has started to construct storm water network on the S-8 expressway section from Przeszkoda to Paszkow.
We will construct storm water line of:
1. PP DN160-DN800 - 6340m
2. PEHD DN150-DN450 - 345m
3. PCV DN200-DN400 - 73m
4. rainforcement chamber DN1200-DN3200 - 231 item
5. concrete chamber DN500 - 247 item
6. underground storage reservoirs
7. sewage treatment plant
P.B.I. PEBIS Sp. z o.o. has signed contract with INTERCOR to build storm water line, sewer line and wather line during reconstruction of Marynarska street in Warsaw.
We have already started to built storm water line DN300 using guided auger boring system with Naylor caly jackig pipes. The depth of boring is abot 7,0meters deep.