S8 Przeszkoda-Paszkow main road extension

S8 Przeszkoda-Paszkow main road extension

 

Investor: GDDKiA
General Contractor: Przedsiębiorstwo Usług Technicznych "Intercor" Sp. z o.o.

P.B.I. PEBIS sp. z o.o. has started to construct storm water network on the S-8 expressway section from Przeszkoda to Paszkow.

We will construct storm water line of:
1. PP DN160-DN800 - 6340m
2. PEHD DN150-DN450 - 345m
3. PCV DN200-DN400 - 73m
4. rainforcement chamber DN1200-DN3200 - 231 item 
5. concrete chamber DN500 - 247 item 
6. underground storage reservoirs
7. sewage treatment plant