Warsaw 2012

Construction of expressway stage III (S-2). Warsaw Southern bypass section from Konotopa junction to the Airport junction.

Investor: Generalna Dyrekcja Dróg Krajowych i Autostrad

General Contractor: BILFINGER BERGER BUDOWNICTWO S.A.

 

In September 2010 P.B.I. PEBIS sp. z o.o. proceeded to the construction of the storm water network on the S-2 expressway from Konotopa to the airport.

 

We constructed:

- storm water network of Glassfiber Reinforced Plastic pipes, diameter from DN200 to DN1200 with a total length of 33960m,

- Glassfiber Reinforced Plastic (GRP) chambers a diameter from  DN1200 to DN1600 – total amount 835,

- reinforced concrete chambers -total amount 152,

- drainage WIPRO pipe a total length 75m,

- catch basins with sumps total amount 1207,

- storage reservoirs of GRP DN1800 to DN3000 pipes a length of 640m,

- assembly of sumps, separators, sewage pumping stations and other,

- bridges drainage.

Construction of expressway stage III (S-2). Warsaw Southern bypass section from Konotopa junction to the Airport junction.

Back [-]
Warsaw 2014Construction of the heating distribution network 2xDN500/710 on the section from Silnikowa street to the border of Ursus district in the area of Tynkarska street.Warsaw 2012Construction of Nowolazurowa street. Implementation of surface drainage for pulling on the tunnel under the railway operation.