Warsaw 2014

Construction of the heating distribution network 2xDN500/710 on the section from Silnikowa street to the border of Ursus district in the area of Tynkarska street.

Investor: ENERGETYKA URSUS SP. Z O.O.

General Contractor: P.B.I. PEBIS SP. Z O.O.

 

PEBIS as a General Contracotr of the heating distribution network in preinsulated steel pipes 2xDN500/710 technology with alarm system Brandes, constructed:


- heating distribution network DN500/710 with all fields - total lenght 800m

- GRP DN924mm pipes as a protective tube - total lenght 95m

- steel protective pipes Dz813x16 - total lenght 24m

- installation of steel protective pipes DN400 - total lenght 93m

- installation of heating distribution network DN200/315 - total lenght 120m

 

Construction of the heating distribution network 2xDN500/710 on the section from Silnikowa street to the border of Ursus district in the area of Tynkarska street.

Back [-]
Warsaw 2014Kadetow street / Panorama IV housing estate, Warsaw 2013